The court ordered the supplier of bulletproof vests to pay UAH 35 million for the delay in deliveries to the Armed Forces of Ukraine

post-img

2 min to read

The Kyiv Commercial Court ordered Ukrtak.UA to pay UAH 35 million in penalties to the Defense Procurement Agency of the Ministry of Defense of Ukraine due to the untimely delivery of body armor.

This was reported by Economic Truth with reference to the court decision.

In October 2024, the state ordered 9,000 modular body armor from the company with a total cost of UAH 254.52 million. The delivery was supposed to take place during November-December, but the delay was from 20 to 110 days.

The Defense Procurement Agency demanded to collect more than UAH 61 million in penalties and fines from the supplier.

The company explained the delay by the seizure of part of the goods by law enforcement officers and insisted that it had finally fulfilled the contract. At the same time, the supplier asked to reduce the sanctions to UAH 446.5 thousand.

The court rejected the company’s arguments regarding force majeure due to the lack of proper evidence.

However, taking into account the absence of losses for the customer and the need to comply with the principle of proportionality of liability, the court reduced the amount of the recovery to UAH 35 million.